In order to participate in the CPS Program, resources must register in PTS and submit a separate SQA application upon registration approval. If not already qualified as a CPS DAS Reporter, Reporter organizations must also complete an application process. The tables below are meant to serve as a general reference for stakeholders on the average application processing times involved in program qualification, and target dates for submissions to be able to participate in each quarter.
| Average Timeframe - PTS Registration Submission to SQA and CPTS Registration | ||||
| Step | Description | Responsible Party | Average Processing Timeframe | Submission Deadline for In-Quarter Participation |
| 1 | PTS Registration Submitted | System Owner or GIS Account Holder | N/A | Q1 - January 15th Q2 - April 15th Q3 - July 15th Q4 - October 15th |
| 2 | PTS System Registration Review and Approval | PTS Team | 7 business days | N/A |
| 3 | SQA Application Submitted | System Owner or GIS Account Holder | Dependent on user | Q1 - February 1st Q2 - May 1st Q3 - August 1st Q4 - November 1st |
| 4 | SQA Application Review and Approval - Program Effective Date Determined | DOER/Cadmus Team | 14 business days | N/A |
| 5 | SQA Registered in CPTS - Requires Approved DAS Reporter | PTS Team | 7 business days | N/A |
| Total Average Processing Timeframe: *28 business days | ||||
| *Applications submitted with incomplete or inaccurate information may experience longer-than-average processing times. *Applicants using a DAS Reporter that has not yet been approved for the CPS program at Step 5 (CPTS Registration) may experience delays until final DAS approval and registration are completed. (Refer to the accompanying quarterly submission deadlines in the DAS Provider Application section.) Please Note: The submission deadline for In-Quarter Participation indicates the cutoff date to ensure participation within a specific quarter. However, all system program participation becomes effective based on the DOER SQA Application approval date. | ||||
| Average Timeframe - New DAS Provider Application to Final DAS Approval | ||||
| Step | Description | Responsible Party | Average Processing Timeframe | Submission Deadline for In-Quarter Participation |
| 1 | DAS Application Submitted & Developer API Account Created | DAS Provider | N/A | Q1 - February 1st Q2 - May 1st Q3 - August 1st Q4 - November 1st |
| 2 | DAS Application Review and Conditional Approval | PTS Team | 7 business days | N/A |
| 3 | DAS API Staging Key Issuance | PTS Team | 5 business days | N/A |
| 4 | API Test Data Submitted and PTS Notified - PTS Account for Reporter Role Created | DAS Provider | Dependent on user | Q1 - May 1st Q2 - August 1st Q3 - November 1st Q4 - January 1st (after close of Q4) |
| 5 | API Test Data Review and Approval - Production Key Issued | PTS Team | 5 business days | N/A |
| 6 | Final DAS Approval & Registration | PTS Team | 3 business days | N/A |
| Total Average Processing Timeframe: 20 business days | ||||