Accuracy Requirements
Metering equipment must meet the accuracy requirements of ISO New England Operating Procedure No. 18 or any successor thereto or the Small Generator Metering Protocol specifications (below) per NEPOOL GIS Rule 2.5(j).
Minimum Accuracy Requirements Only "revenue grade" (also called "revenue quality") meters tested and certified to ANSI C-12 standards are allowed. Minimum accuracy and other requirements, based on nameplate capacity, are as follows: |
||||
Nameplate |
|
Minimum Meter Accuracy |
|
Other Requirements |
Up to 10 kW, using non-automated reporting Meters used as part of a Data Acquisition System (“DAS”) must meet the "Greater than 10 kW and up to 1 MW" nameplate capacity requirements below. |
|
2% |
|
Electromechanical meters may be used. Refurbished meters, if retested and certified, may be used. Allowable configurations for meters are :
|
Greater than 10 kW and up to 1 MW |
|
1% |
|
Only new solid state meters are allowed. Current transformers (“CTs”) must conform to the 0.6% (ANSI/IEEE C57.13-2008) accuracy class, or the meter must be tested using the CT and certified to meet the minimum accuracy requirement. |
Greater than 1 MW |
|
0.5% |
|
Only new meters are allowed. CTs must conform to the 0.3% (ANSI/IEEE C57.13-2008) accuracy class. |
Meter Testing and Calibration
Meters shall be tested, and as needed calibrated or replaced, in accordance with Table 2 below.
Meter Testing Requirements |
||
Category |
Minimum Frequency |
Other Requirements |
Up to 10 kW |
None |
MassCEC at its discretion may require testing or replacement of a meter associated with unreasonable energy production reports. |
Greater than 10 kW and up to 500 kW. |
As required by DAS Vendor requirements and best practices |
DAS Vendors are required to demonstrate energy reports to the PTS are within +/- 1% of the meter registry for an individual system. MassCEC at its discretion may require testing or replacement of meter associated with unreasonable energy logged by the meter registry. |
Greater than 500 kW |
At least once every two years per NEPOOL OP18 |
Only new meters are allowed. CTs must conform to the 0.3% (ANSI/IEEE C57.13-2008) accuracy class. |
Solar Meter Placement
The solar PV production meter may be installed at any point between the AC output of an inverter and the point of interconnection with the electric grid.
As an alternative, energy reported from a utility owned net-meter installed on the utility side of the electric service may be used in lieu of a solar production meter where:
- the output from a solar PV inverter is interconnected on the utility side of the electric service
- as long as the PV array is the only generator or energy storage system behind the utility net meter.
Treatment of Parasitic Load
Per the Renewable Energy Portfolio Standard (RPS) 225 Code of Massachusetts Regulations (CMR) 14.02, energy consumed by parasitic load, which is not otherwise accounted for by the solar PV production meter, must be excluded from reported generation values.
For the purposes of SREC II metering requirements, unaccounted for parasitic load is defined as the tare loss associated with nighttime energy consumption by an inverter. Tare loss of less than or equal to the levels listed below (as reported by the inverter manufacturer) is deemed to be de minimis and is not required to be excluded from the meter reading. When bi-directional (net) meters are used to report production the value reported shall be the “delivered” energy, not the “net” energy.
Inverter Rated Output |
Tare Loss de minimis Level (Watts) |
10 kW or less |
30 |
Greater than 10 kW up to 100 kW |
330 |
Greater than 100 kW up to 1 MW |
3,330 |
Greater Than 1 MW |
8,200 |
If the tare losses of an individual inverter exceed the de minimis levels contact MassCEC for further guidance on reporting.
Multiple Inverter Systems
Multiple inverter systems which combine output power from the multiple inverters before interconnecting to the gird, and which are registered in the PTS as a single PV system, shall have only one meter that measures the combined energy output.
Meter Labeling
PV system meters shall have weather resistant labeling that clearly associates the meter with the PV system. For example “PV Production Meter.”
Meter Start
All new and refurbished meters shall be set at 000000 or 999999 at time of shipment to the installer to ensure accurate and consistent “start” readings for every system.
Meter Warranty
A meter warranty of not less than one year is required on all new and refurbished meters.
Comments
0 comments
Article is closed for comments.